Closing Cabinet Jobs Without Leaving Inventory and Labor Open
Job closeout should confirm that the relevant work and records have reached a defined endpoint.
Archive ·Comparing estimated and actual labor is useful only when both describe the same scope and operations.

Comparing estimated and actual labor is useful only when both describe the same scope and operations. Preserve the original estimate, then identify approved changes, rework, and missing entries before interpreting the variance. A larger total is a starting point for investigation.
A hypothetical assembly estimate is 80 hours and recorded effort is 92. The variance is 12 hours, or 15% of the estimate. If eight hours belong to an approved addition, the unexplained original-scope difference is four hours, not twelve.
Record what caused the remaining difference and whether it is likely to recur. Change an estimating assumption only when the evidence supports it.
Use Millbase project tracking to keep a cabinet job and its sub-projects together, then compare estimates with recorded labour and material costs. Insights and reports help the team inspect the people and workstations behind a total and export supported results for the next review.
Ask the Millbase AI agent a question grounded in your workspace records. For example: “Compare this project’s estimated and actual labour, then break the logged hours down by workstation.” You can select a project or worker, ask follow-up questions, and request supported reports and CSV exports.
Check the date range, job scope, and recorded inputs before changing a quote. Keep the accounting treatment of overhead, tax, and revenue in the appropriate financial process; a shop-floor cost breakdown is only as complete as the inputs recorded.
For the broader workflow and decisions behind this guide, read Cabinet Shop Job Costing: Separate Margin From Markup.
Maintain a current forecast, but preserve the original baseline. Otherwise the final review cannot show what changed.
No. Scope, missing material, rework, training, and inaccurate estimates can all contribute. Review the context before drawing that conclusion.